Paving Block Replacement at West Jakarta Mayor Office Reaches 85 Percent
access_time July 26 2024 11:36 AM remove_red_eye 144
Reported by TP Moan Simanjuntak | Translated by Rizky Mawardi
Reported by TP Moan Simanjuntak | Translated by Rizky Mawardi
The paving block replacement work on the left side of West Jakarta Mayor Office yard is being accelerated. Now the work has reached 85 percent out of 476.42 square meter.
We replace it with the new one
West Jakarta City Administration Secretary General and Protocol Division Head, Mera Nuringsih, said paving blocks were replaced because many were damaged, such as broken and chipped, endangering pedestrians and passing vehicles.
"We replace it with the new one," she said, Thursday (7/25).
Road Repair on Jalan Rawa Indah CompletedAccording to her, the work was started on June 21, 2024 and is targeted to complete on August 5, 2024.
"Now the progress reaches 85 percent," she admitted.